Make a task wait for something

How-to

Make a task wait for something

Record that a task waits for another task, a document, an outside party, an approval or a date.

What you need to know

A records what a task waits for: another task, a document, an outside party, an approval or a date. You add it to a draft version, on Dependencies. Every project started from the version after it is published has it. You need to be a department manager or a company administrator.

Before you start

  • The version is a draft. A published version cannot change: revise it first.
  • The task that waits, and any task it waits for, are already on Tasks.

What to do

  1. Open the template from Workflow Templates and select Edit on the draft. In the left menu, select Dependencies.
  2. Under Add a dependency, below the list, in What kind of waiting, choose what it waits for (see the table below). The form asks this first, with nothing chosen, and shows the other fields once you choose.
  3. In Task, choose the task that waits, then fill in the fields that appear. Here, a task waits for Legal's approval:

    Template editor · Dependencies · Add a dependency

    Example · sample data

    Add a dependency

    1. What kind of waiting. Waiting on approval.
    2. Approver. Who must approve: Legal, Accounting or Executive.
    3. Enforcement. Blocks the task, the choice the form starts with.
  4. In Enforcement, choose how strict the wait is.
  5. Select Add dependency. The new row is in the list, and the form asks the kind of waiting again for the next one.
The task depends on
Choose
Another task being finished first
Blocked by another task
Another task staying as it is: a change to that task makes this task’s result out of date
Invalidated by another task
A document from outside
Waiting on an external document. Tick every document it needs.
An outside party, such as the client, reaching a point
Waiting on an external party, with the Party and the Required relationship stage.
An approval by Legal, Accounting or Executive
Waiting on approval, with the Approver.
A day, counted from a start or a date on the record
Waiting until a date, with the Anchor and Offset (days).
No records

For a date, the form says “Negative means before the anchor, positive means after.” So an Offset (days) of 30 with the Anchor Project started waits until 30 days after the project starts. With the Anchor Pre-reassessment call and an offset of 0, the task waits until the day of the call, three months before the state's notice date.

Confirm it worked

The list under What each task is waiting on has a new row: the task, the kind of waiting and what it waits for. The line under the title counts one more dependency.

If it did not work

  • Add dependency cannot be selected: a field marked with a star is still empty. For Other (describe below), also type what the document is in Which document.
  • There is no Add a dependency section: the version is published or retired. Revise it first: Change a published template.
  • A message at the bottom right says the dependency was not added. The form keeps what you chose, so you can try again. If you ticked several documents and some saved, the message says how many, and the form keeps only the rest.
  • Publish later refuses because tasks wait for each other in a circle: change or delete one of the dependencies in the circle. See Publish checks.

Good to know

What a running project does with each kind of waiting is in How a task waits.